- CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project
Motion to approve CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project to Traffic Control & Engineering Co. in the amount of $97,041.56.
Discussed at meetings:
Meeting BOSAP - 9/2023 on 9/28/2023 by Board of Supervisors - Agenda Preparation Meeting Status: Finished
Topic: Contract Payments
Topic: Contract Payments
Minutes: No.9
CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project
At the October 5, 2023 Regular meeting, the Board will be asked to consider approval of CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project to Traffic Control & Engineering Co. in the amount of $97,041.56.
CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project
At the October 5, 2023 Regular meeting, the Board will be asked to consider approval of CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project to Traffic Control & Engineering Co. in the amount of $97,041.56.
Meeting BOSREG - 9/2023 on 10/5/2023 by Board of Supervisors - Regular Meeting Status: Finished
Topic: Contract Payments
Topic: Contract Payments
Minutes: No.9
CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project
Motion to approve CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project to Traffic Control & Engineering Co. in the amount of $97,041.56.
Votes: Yes 4 , No 0 , Abstain 0
CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project
Motion to approve CAR #23-08-04 - Partial Payment - Route 19 & Progress Avenue Signal Project to Traffic Control & Engineering Co. in the amount of $97,041.56.
Votes: Yes 4 , No 0 , Abstain 0