Voting Details

Community Park North Design & Engineering Update - Environmental Permitting Fees

Staff will present an update to the Board on the ongoing design and engineering for the Community Park North project. The project requires environmental permitting and mitigation. Staff is requesting authorization to continue the design process and authorize submission of permits and payment of the required fees to continue the permitting process.

Motion to authorize the commitment of $379,310 towards the environmental permits and fees for Community Park North as required by the State Environmental Regulations and the County Conservation District.

For: 5
  • John Skorupan
  • Bruce Mazzoni
  • Mike Manipole
  • Bruce Hezlep
  • Karen Newpol
Against: 0
Abstained: 0
Recused: 0
Absent: 0