Laurel Point Temporary Pump Station Agreement

The Laurel Point Development submitted plans for review for a Temporary Pump Station while the permanent pump station is constructed. The temporary pump station is to be in use for a limited number of residential connections of 24 units for a maximum timeframe of 24 months. The agreement has been reviewed by the Solicitor and staff is recommending approval of the agreement.

Motion to approve an agreement with Pikewood Land Partners, LLC. for the Laurel Point Development Temporary Pump Station with 24 units with a maximum timeframe of 24 months.

For: 4
  • John Skorupan
  • Bruce Mazzoni
  • Richard Hadley
  • Mike Manipole
Against: 0
Abstained: 0
Recused: 0
Absent: 0