Purchase Approval #24036 - Independent Engineer's Review for the design of the Brush Creek Water Pollution Control Facility Solids Handling Upgrade
- Number:
- 396/2023
- Description:
- Purchase Approval #24036 - Independent Engineer's Review for the design of the Brush Creek Water Pollution Control Facility Solids Handling Upgrade
The Township has been working on the Solids Handling Upgrade for the Wastewater Treatment Plant. The design is currently at 90% completion. The current engineer's estimate is approximately $35 million. Best practice is to conduct an Independent Engineer's Review to ensure the design meets the Townships needs.
Motion to approve Purchase Approval #24036 - Independent Engineer's Review for the design of the Brush Creek Water Pollution Control Facility Solids Handling Upgrade to HRG/Herbert Rowland & Grubic, Inc., in the amount of $45,600.
Discussed at meetings:
Meeting BOSReO - 1/2024 on 1/2/2024 by Board of Supervisors - Re-Organization Meeting Status: Finished
Topic: Other Business Pertinent to the Township
Topic: Other Business Pertinent to the Township
Minutes: No.23
Purchase Approval #24036 - Independent Engineer's Review for the design of the Brush Creek Water Pollution Control Facility Solids Handling Upgrade
The Township has been working on the Solids Handling Upgrade for the Wastewater Treatment Plant. The design is currently at 90% completion. The current engineer's estimate is approximately $35 million. Best practice is to conduct an Independent Engineer's Review to ensure the design meets the Townships needs.
Motion to approve Purchase Approval #24036 - Independent Engineer's Review for the design of the Brush Creek Water Pollution Control Facility Solids Handling Upgrade to HRG/Herbert Rowland & Grubic, Inc., in the amount of $45,600.
Votes: Yes 5 , No 0 , Abstain 0
Purchase Approval #24036 - Independent Engineer's Review for the design of the Brush Creek Water Pollution Control Facility Solids Handling Upgrade
The Township has been working on the Solids Handling Upgrade for the Wastewater Treatment Plant. The design is currently at 90% completion. The current engineer's estimate is approximately $35 million. Best practice is to conduct an Independent Engineer's Review to ensure the design meets the Townships needs.
Motion to approve Purchase Approval #24036 - Independent Engineer's Review for the design of the Brush Creek Water Pollution Control Facility Solids Handling Upgrade to HRG/Herbert Rowland & Grubic, Inc., in the amount of $45,600.
Votes: Yes 5 , No 0 , Abstain 0